Timeline Estimator
Estimate the build schedule from the same model as the cost calculator, then compare modular and traditional construction.
- Site preparation3 wk
- Foundation3 wk
- Factory build and set5 wk
- MEP and finishes3 wk
- Inspections and closeout2 wk
Modular construction
4 months
Traditional construction
7 months
This schedule uses the cost calculator’s timeline model. It is a planning estimate, not a permit commitment. City review times vary.
Preapproved plan schedules
The Studio
400 sq ft · permit 4-6 weeks · build 8-10 weeks
The One Bedroom
650 sq ft · permit 5-7 weeks · build 10-12 weeks
The Two Bedroom
850 sq ft · permit 6-8 weeks · build 12-14 weeks
The Deluxe
1000 sq ft · permit 6-8 weeks · build 14-16 weeks
The Compact One Bedroom
500 sq ft · permit 4-6 weeks · build 8-10 weeks
The Family Unit
1200 sq ft · permit 7-9 weeks · build 16-20 weeks
The Garden Studio
350 sq ft · permit 3-5 weeks · build 7-9 weeks
The Accessible One Bedroom
700 sq ft · permit 5-7 weeks · build 12-14 weeks